[ Apply | Log In ]
GSO will normally dispatch the lowest-cost generation to meet system demand. A system constraint is applied in the Grid operation’s generation dispatch when the unconstrained dispatch does not allow GSO’s operation to meet the TSRS(Transmission System Reliability Standards)’s Performance Criteria and Limits. For example, system constraint shall be applied to generation dispatch under conditions whereby transmission assets are expected to be operated above their thermal capacity limits under basecase condition or under any defined contingency event. GSO shall conduct appropriate system studies and publish system constraints which may be applied under:

  1. Existing Constraint – when the Grid system are all intact without major impacting system outages but due to inherent Grid system shortcomings, lowest-cost generation dispatch may not be possible and may result in unsecure system operation. Existing Constraint shall be published until Grid system shortcomings are lifted.
  2. Constraints Due to Outage – conditions when the Grid system has to deal with an outage situation when some assets are not available. Constraints Due to Outage shall be published as an information seven days ahead until the outage is normalised.
Existing Constraints
Existing Constraint is described by its type of constraints such as inter-area power transfer limitation; circuits in the Grid being constrained; transmission assets’ voltage and thermal limits impacted by the constraint; quantum of generation limit to be limited from which generation clusters; and some additional operational remarks if any.
TypeConstrained CctVoltageMax Overload(%)Generation LimitGeneration ClusterOther
Basecase275kV and 132kV cables into Penang Island132100GLGR Min = 70GLGRMin 1 GLGR GT on-bus required for thermal loading control and voltage support in Penang Island during weekdays
Contingency275kV ATWR-PRMS-SGRI-BGJH-TPAH-BTRK (2x683 MVA)275150Limit based on max secured Perak-Central Area transferNorthernLimit to the max secured Perak-Central Area transfer to cater for thermal overload and system stability under n-2 contingency of 500kV BTRK-JMJG & BTRK-ATWR
1
Constraints Due to Outage (for the next 7 days)
Constraints Due to Outage is described in similar manner however additional information is included which is the outage duration period of the transmission assets giving rise to the system constraints.
StartEndTypeConstrained CctVoltageMax Overload(%)Generation LimitGeneration ClusterOther
NIL
Regional Generation Availability
Generation Clusters are defined as the composition of major generators with distinctive generation-transmission operation boundaries.
  • Northern Generation Cluster is composed by PLPS, GLGR, SKSP, NPRI, SGRI, SGB3, JMJG, JMJG4, MJG5, BSIA, TMGR, KNRG, LPIA, UPIA, CEND, UJLI, SYPS and SIHY generators.
  • Eastern Generation Cluster is composed by PGAU, HTRG, KNYR and YTL PAKA generators.
  • Southern Generation Cluster is JMHE, TJPS, PGLA, TBIN, TBIN4, PGPS, PCGP and SPGP generators.
  • Central Generation Cluster is composed by PKLG, CBSB, PJPS, KLPP and JMAH generators.
DateMW
26 Oct 2020 22677
27 Oct 2020 23112
28 Oct 2020 23496
29 Oct 2020 23779
30 Oct 2020 23779
DateMW
26 Oct 20208106
27 Oct 20208106
28 Oct 20208106
29 Oct 20208106
30 Oct 20208106
DateMW
26 Oct 20208603
27 Oct 20209038
28 Oct 20209422
29 Oct 20209422
30 Oct 20209422
DateMW
26 Oct 20201500
27 Oct 20201500
28 Oct 20201500
29 Oct 20201500
30 Oct 20201500
DateMW
26 Oct 20204468
27 Oct 20204468
28 Oct 20204468
29 Oct 20204751
30 Oct 20204751